The location shown on the map is approximate at this stage.
The application is expected to be submitted to the IPC on 1 October 2012.
The IPC has 28 days from the day after submission (known as the acceptance stage) to review the application and decide whether or not to accept it.
If the application is accepted, we will advise the timescales when interested parties can register to make a representation.
If the application is accepted, we will:
Bramford to Twinstead Overhead Line
Location
Linear route West of IpswichType of project
Electric LinesDeveloper
National GridDeveloper's contact
National Grid Communication - tel. 08003777340The location shown on the map is approximate at this stage.
Additional project information
400kv Electricity Line (Approx 25-30km in length) which will enable grid connection to Sizewell C.Local Authorities: Babergh District Council, Suffolk County Council, Braintree District Council, Essex County Council.
Four options have been put forward for Stage 1 of public consultation, which closed on 22 February 2010.
What happens next
The application is expected to be submitted to the IPC on 1 October 2012.
The IPC has 28 days from the day after submission (known as the acceptance stage) to review the application and decide whether or not to accept it.
If the application is accepted, we will advise the timescales when interested parties can register to make a representation.
If the application is accepted, we will: