The location shown on the map is approximate at this stage.
Additional project information
Development of approximately 7,200MW of wind capacity off the coast of East Anglia, known as Zone 5, under the Round 3 Offshore Wind Licensing Arrangements. A joint venture between Scottish Power Renewables and Vattenfall Wind Power.
What happens next
The application is expected to be submitted to the IPC on 1 November 2012.
The IPC has 28 days from the day after submission (known as the acceptance stage) to review the application and decide whether or not to accept it.
If the application is accepted, we will advise the timescales when interested parties can register to make a representation.
If the application is accepted, we will:
Publish all the application documents at our website
Publish the date from which you will be able to register to put your case on the application
Publish the date on which registration will close.
East Anglia Offshore Windfarm
Location
14 km off Norfolk/Suffolk coastType of project
Generating StationsDeveloper
Scottish PowerDeveloper's contact
Helen Thompson - tel. 01416140444The location shown on the map is approximate at this stage.
Additional project information
Development of approximately 7,200MW of wind capacity off the coast of East Anglia, known as Zone 5, under the Round 3 Offshore Wind Licensing Arrangements. A joint venture between Scottish Power Renewables and Vattenfall Wind Power.What happens next
The application is expected to be submitted to the IPC on 1 November 2012.
The IPC has 28 days from the day after submission (known as the acceptance stage) to review the application and decide whether or not to accept it.
If the application is accepted, we will advise the timescales when interested parties can register to make a representation.
If the application is accepted, we will: